Anadarko Delaware Basin Development
Delaware Basin
Project Description
Customer Challenge
Area A includes over 245 miles of pipelines ranging from 8-in. to 24-in. to gather and transport oil, LP gas, HP gas, and produced water.
Our Solution
HGA began the field alignment surveys at the end of this year as permissions were given by landowners, and completed the initial fieldwork within six weeks. The resulting surveys allowed HGA’s pipeline designers to start the next major undertaking of producing all of the property plats. The first plats were issued in less than two weeks, and over the next six weeks, approximately 540 plats were issued. This is in large part due to the quality of HGA’s field survey staff and HGA’s advancements in the utilization of GIS technology. HGA also prepared approximately 470 pipeline alignment sheets by the end of May, and approximately 145 piping drawing packages by the end of June, a total of 390,000 man hours in 18 months.
The scope of services included:
- Detailed Engineering Services for both Pipeline and Facilities
- Route Selection
- Surveying – Preliminary thru Construction
- Procurement Support
- Project Controls Tracking & Reporting
- Progress Curves/Trend analysis
- Scheduling & Reporting
- Job Books